Tuesday, May 17, 2011

Resource Management

1. Which of the following is NOT a human resource process?
A. Develop Resource Plan
B. Acquire Resources
C. Report Team Performance
D. Develop PTeam

2. Which of the following is NOT a tool used in Develop Team
A. Interpersonal Skills
B. Training
C. Ground rules
D. Encouragement

3. If you hear a project manager saying to a customer “we all agree that this project is important. Let’s not fight over a few thousand dollars, what conflict resolution technique is the project manager trying to use?
A. Smoothing
B. Problem Solving
C. Forcing
D. Compromising

4. What is considered the LEAST desirable form of power for a project manager to exercise?
A. Formal
B. Referent
C. Punishment
D. Forcing

5. Which of the following Enterprise Environmental factors is NOT a relevant input for Human Resource Planning process:
A. Hiring Freeze
B. Supervisor-subordinate relationships
C. Technical competencies of project staff
D. Individual goals and agendas of project stakeholders
E. Reduced Training Funds
F. Organizational Chart Templates


6. Which of the following is the most important element of Project Management Plan that is useful in HR Planning process:
A. Risk Management activities
B. Quality Assurance activities
C. Activity Resource requirements
D. Budget Control activities

7. All of the following can be used to document team member roles and responsibilities EXCEPT:
A. Hierarchical-type Organizational Chart
B. Matrix-based Responsibility Chart
C. Text-oriented Format
D. Functional Chart

8. Resource Breakdown Structure is an example of:
A. Hierarchical-type Organizational Chart
B. Responsibility Assignment Matrix
C. Text-oriented Format
D. Functional Chart

9. Which of the following types of Organizational Charts can be BEST used to track project costs :
A. Hierarchical-type Organizational Chart
B. Organizational Breakdown Structure
C. Resource Breakdown Structure
D. Responsibility Assignment Matrix

10. Which of the following is not true for a Responsibility Assignment Matrix (RAM):
A. Defines what project team is responsible for each WBS component
B. Defines what project member is responsible for each activity
C. Text description of roles, responsibilities, authorities
D. Defines all people associated with each activity

11. War room creation during project deployment phase is an example of:
A. Team Building activity
B. Establishing Ground Rules
C. Co-Location
D. General Management Skills

12. Building a virtual team for a project will limit the usability of which of the following tools and techniques for Team Development:
A. Team Building
B. Establishing Ground Rules
C. Co-Location
D. Reward and Recognitions

13. The lowest point of Maslow’s Hierarchy of needs is:
A. Physiological
B. Social
C. Security
D. Self-actualization

14. Which of the following conflict-resolution techniques will provide the most lasting solution?
A. Withdrawing
B. Problem solving
C. Forcing
D. Compromising

15. Which is the best power for motivating the team members?
A. Referent power
B. Punishment power
C. Reward power
D. Legitimate power

Answers
1. C
2. D
3. A
4. C
5. F. A & E are examples of constraints placed upon the project by current organizations policies and fall in the domain of Enterprise Environmental factor. B, C & D are valid Enterprise Environmental factor. F is actually an element of Organizational Process Asset (not Enterprise Environmental factor).
6. C. Activity Resource requirements is a primary input to HR Planning. It is used to determine the human resource needs of the project.
7. D. Functional Chart is not listed in PMBOK as a type of Organizational Chart
8. A
9. C. A RBS can be aligned with Organization’s accounting system
10. C.
11. C
12. C
13. A
14. B
15. C

For training and consulting go to --->    www.pmexpertinc.com


PMP Procurement Management

Assess your knowledge level  on Project Procurement  Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions


Click to Start  >>>Project Procurement  Management - Online Sample Test


Project Procurement Management PPTs



Additional Questions on Project Procurement Management

1. Your company is outsourcing a project in an area where it has little experience. The procurement document should be
A. Completely rigid to ensure no deviation from sellers
B. Flexible enough to encourage creativity in seller responses
C. Informal
D. Reviewed by senior management

2. In your project, your subcontracting requirements of the machining of high-value equipment are very demanding. Hence, you have determined the technical criteria to evaluate the sellers. This is an example of:
A. Objective evaluation criteria
B. Source selection criteria
C. Statement of work
D. Work breakdown structure

3. Which of the following represents the right sequence of processes?
A. Analyze Procurements, Plan Procurements, Conduct Procurements, Close Procurements.
B. Determine Make or Buy, Administer Procurements, Conduct Procurements, Close Procurements
C. Plan Purchases and Acquisitions , Administer Procurements, Conduct Procurements, close procurements
D. Plan Procurements, Conduct Procurements, Control Procurement

4. The contract type that represents the highest risk to the seller is:
A. Fixed price plus incentive
B. Cost reimbursable
C. Fixed price
D. Cost reimbursable plus incentive

5. Make –or – buy analysis is a tool used in which process?
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Analyze Procurements

6. Process of Administer procurements falls under which process group
A. Planning
B. Closing
C. Monitoring and Control
D. Executing


7. ABC Consultancy has a large internal project to be initiated. To staff this project, ABC Consultancy is working with People Consultancy to provide three resources for six months. The resources will be part of the team managed by ABC Consultancy for six months. Which contract type should be used by Sam Consultancy?
A. Purchase Order
B. Cost plus Fee
C. Fixed cost
D. Time and Material


8. Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer store. Which type of contract will get signed in this case?
A. Purchase Order
B. Cost plus Fee
C. Fixed cost
D. Time and Material


9. ABC Consultancy is getting 200 computers installed from a vendor. The vendor will be paid the cost involved and a 10% incentive. Which contract will be used in this case?
A. CPPC
B. CPIF
C. CPFF
D. Fixed Cost


10. Monika is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress?
A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements


Answers
1. B
2. B
3. D
4. C
5. A
6. C. Administer procurements is part of Monitoring and Control process group.
7. D. This is a case of Staff Augmentation. These projects are managed in Time and Material.
8. A. Purchase Order is used i.
9. A. Cost plus percentage of the cost
10. A. During the Conduct Procurement process, bidders can clarify their doubts using bidder conference

For training and consulting go to --->    www.pmexpertinc.com

Communication Management

Assess your knowledge level  on Project Communication Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions

Click to Start  >>>Project Communication  Management - Online Sample Test

Project Communication Management PPTs

Additional Questions

1. The majority of a person’s communication is :
a. Verbal
b. Non-Verbal
c. Documented
d. Unnecessary

2. Communication skills would be used most during which of the following processes?
a. Manage Communication
b. Status Meetings
c. Report Performance
d. Communication Change Control

3. In which process would earned value analysis be used
a. Plan Communication
b. Distribute Information
c. Control Cost
d. Report Project Value

4. John is using forecasting to determine her project’s estimate at complete. What would be the most likely place to include this information?
a. The communication management plan
b. The project activity report
c. The performance reports
d. The stakeholder management report

5. Lessons learned should contain
a. The collective wisdom of the team
b. Feedback from the customers as to what you could have done better
c. Information to be used as an input into administrative closure
d. Analysis of the variance that occurred from the project’s baseline

6. The most important skill for a project manager to have is
a. Good Administrative skills
b. Good Planning skills
c. Good Client-facing skills
d. Good communication skills

7. The process of Manage Stakeholders Engagement is part of which process group?
a. Planning
b. Monitoring and Control
c. Executing
d. Initiating

8. The project you are managing has nine stakeholders. How many channels of communications are there between these stakeholders?
a. 9
b. 8
c. 45
d. 36

9. Which of the following is not an example of formal communication?
a. Contract
b. email
c. Project status report
d. Status meeting

10. Which of the following process is not included in project communication knowledge area?
a. Documenting Project Closure
b. Plan Communications
c. Distribute Information
d. Managing Stakeholder Expectations

11. The sender is responsible for:
a. Confirming the message is understood
b. Ensuring the receiver agrees with the message
c. Scheduling communication exchange
d. Presenting the message in the most agreeable manner

12. You present a status report of your project to the account executive in a meeting. This is an example of:
a. Formal verbal
b. Informal verbal
c. Formal written
d. Informal written'

13. Which communication process is part of Initiating process group?
a. Identify Stakeholders
b. Manage stakeholder engagement
c. Distribute information
d. Plan communication

14. You ask the status of the project from the team lead and the answer tou get is “everything is fine” in a strange tone. This is an example of:
a. Active listening
b. Nonverbal
c. Para lingual
d. Feedback

15. A stakeholder with high interest and low power must be kept Informed of your project’s progress
a. False
b. True

16. There are 15 members in a group. The Project manager realizes that the number of communication channels high. He therefore decides to make smaller groups of 5 members each with one group leader each. The members formally communicate within the group only, while the inter-group communication is through group leaders only. What is the number of communication channels within and across the Groups now (excl. the Project Manager)?
 a.105
 b. 33
 c. 108
 d. 30

17. There are five teams in a project , each having 5 members including a team lead.The inter team communication happens only through team leads. The number of communication channels are

 a) 60
 b) 300
 c) 85
 d) None of the above

 
Answers
1. b
2. a
3. c
4. c
5. b
6. d
7. c. Manage Stakeholder Engagement is part of executing process group.
8. d. There will be (9*8)/2 channel of communication.
9. b. Communication via email is not considered a formal communication.
10. a. Document Project Closure is not a process in Project communication knowledge area.
11. a
12. a
13. a
14. c
15. b
16. b
17. a

For training and consulting go to --->    www.pmexpertinc.com

Project Risk Management


Assess your knowledge level  on Project Risk  Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions

Click to Start 20 randomly selected questions on Project Risk Management

1. Based on the following data
(Probability -P, Impact -I, Expected Value = P X I)
What is the amount needed for the contingency fund ?

Risk - 1 (.35, -4000, -1400)
Risk - 2  (.40, 50000, 20000)
Risk -  3 (.45, -300000, - 135000)
Risk - 4 (.30 ,50000 ,15000)
Risk - 5 (.35, -45000, - 15750)


a. Unknown with this information
b. 249,000
c. 117,150
d. 15750

2. Risk Identification is considered to be_________________
a. Iterative
b. Self-led
c. Mandatory
d. Optional
3. Which of the following can determine multiple scenarios with risk and probability of impact
a. Decision trees
b. Monte Carlo simulations
c. Pareto charts
d. Gantt charts

4. Risks that include fire, theft, or injury and offer no chance for gain are
a. Business Risks
b. Pure Risks
c. Risk acceptance
d. Life risks
5. Which of the following is not an input to risk management planning?
a. The project charter
b. Risk Identification
c. Defined Roles and Responsibilities
d. WBS

6. John has joined as the Project Manager of a project. One of the project documents available to John lists down all the risks in a hierarchical fashion. What is this document called?
a. Risk Management Plan.
b. List of risks.
c. Monte Carlo diagram.
d. Risk Breakdown Structure.

7. Which of the following statements is true about risks?
a. When evaluating risks their impact should be considered, however probability of occurrence is not important.
b. Risks if they happen always have negative impact and not positive.
c. Risk register documents all the risks in detail.
d. Risk response plan is another name for Risk Management Plan.

8. David is the Project Manager of a Road construction project. During a project review, David realizes that one particular risk has occurred. To take appropriate action against risk that has happened, David needs to refer to which document?
a. Risk response plan
b. Risk management plan
c. Risk breakdown structure
d. Risk register

9. During which stage of Risk planning are risks prioritized based on probability and impact?
a. Identify Risks
b. Plan Risk responses
c. Perform Qualitative risk analysis
d. Perform Quantitative risk analysis

10. During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?
a. Identify Risks
b. Plan Risk responses
c. Perform Qualitative risk analysis
d. Perform Quantitative risk analysis


11. David is a Project Manager for Green Valley project. A risk management plan has been prepared for the project. Which of the following should David do next?
a. Perform Qualitative risk analysis
b. Perform Quantitative risk analysis
c. Identify Risks
d. Plan Risk responses

12. Which of the following processes has risk register as the primary output?
a. Plan Risk Management
b. Identify Risks
c. Monitoring and Control Risks
d. Perform Qualitative Risk Analysis

13. Five of the processes in Project Risk Management are from which process group?
a. Initiating
b. Planning
c. Executing
d. Monitoring and Control

14. Monika is a Project Manager for a reforestation project. To identify the risks involved, John sends a questionnaire to gather inputs from experts. Which technique is Monika using?
a. Delphi technique
b. Interviews
c. Brain storming
d. Documentation review


15. Mathew is a Project Manager for software migration at a bank. A major risk that has been identified is attrition of resources. As a strategy to respond to this risk, Mathew, with support from Senior Management, provides good increments to his team members. What type of risk response is Mathew following?
a. Accept
b. Avoid
c. Transfer
d. Mitigate


Answers
1. C-117150 is the correct answer
2. a
3. b. Monte Carlo simulations can reveal multiple scenarios
4. b. Pure risks are the risks that could threaten the safety of the individuals on the project
5. b. Risk Identification is not an input to risk management
6. d. Hierarchical description of risks is called Risk Breakdown structure.
7. c. Risk register documents the risks in detail.
8. a. David needs to refer to the Risk response plan that documents responses to identified risks.
9. c. Risk probability and impact are defined during Qualitative risk analysis.
10. d.

11. d
12. b. Process of Identify Risks has Risk register as the major output.
13. b. Five of the six processes in Project Risk Management are part of the Planning process group.
14. a. Monika is using the Delphi technique to identify risks.
15. d. Mathew is mitigating the risk by reducing the probability of risk happening

For training and consulting go to --->    www.pmexpertinc.com

Quality Management

Project Quality Management online sample Question


1. If the results of activity A have no bearing on the results of activity B, the two activities would be considered
A. Statistically Unique
B. Statistically independent
C. Correlated but not casual
D. Mutually exclusive

2. Plan Quality includes all of the following outputs EXCEPT:
A. Quality management plan
B. Acceptance
C. Operational definitions
D. Checklists

3. Which of the following is most representative of the Total Quality Management philosophy?
A. Decreasing inventory to zero or near zero levels
B. Everyone can contribute to quality
C. Zero defects
D. Continuous improvement is preferred over disruptive change

4. On a control chart, the customer’s acceptable quality limits are represented as:
A. Control limits
B. Mean
C. Specifications
D. Normal distribution

5. Which of the following is NOT a part of the Plan Quality process
A. Benchmarking
B. Audits
C. Cost-benefit analysis
D. Design of experiments

6. Process Analysis is a function of:
A. Performance Analysis
B. Quality Metrics
C. Process Improvement Plan
D. Quality Improvement Plan

7. Root Cause Analysis relates to:
A. Process Analysis
B. Quality Audits
C. Quality Control Measurements
D. Performance Measurements

8. Trend Analysis is often performed using:
A. Cause and Effect Diagram
B. Control Charts
C. Pareto Chart
D. Run Chart
E. Scatter Diagram

9. A Pareto diagram can be best described as:
A. Cause and Effect Diagram
B. Scatter Chart
C. Control Chart
D. Histogram

10. A planning phase for an engineering component generated 80 engineering drawings. The QA team randomly selected 8 drawings for inspection. This exercise can BEST be described as example of:
A. Inspection
B. Statistical Sampling
C. Flowcharting
D. Control Charting

11. Perform _______________ is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
A. Quality Control
B. Quality planning
C. Quality Assurance
D. Process Control

12. A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:
A. Statistical Histogram
B. Juran Histogram
C. Fishbone Diagram
D. Pareto Diagram

13. Which of the following is not considered a cost of nonconformance to quality?
A. Scrap
B. Rework
C. Expediting
D. Process control
14. 80% of the problems are found in 20% of the work is a concept of:
A. Edward Deming
B. Philip Crosby
C. Juran
D. Pareto

15. _____________________ is a statistical method that helps identify which factors might influence specific variables
A. CPM
B. Design of Experiments
C. Statistical sampling
D. Benchmarking

 
Answers
1. B
2. B
3. B
4. C
5. B
6. C. A is incorrect as it relates to performing measurements to present performance. B is incorrect as it relates to the specific measurements that shall be performed on the project work in order to measure quality. C is correct because process analysis is simply execution of the steps outlined in Process Improvement Plan D is incorrect because Process Improvement Plan is not a part of Quality Improvement Plan (per PMBOK)
7. A. The option B is incorrect because a Quality Audit is to identify inefficiencies, non-compliance in project activities. It does not necessarily identify the root cause.
8. D. Run Chart shows the past pattern of variation. Trend Analysis involves forecasting the future trend based on past performance.
9. D. Note that Pareto diagram is not the best tool for root-cause analysis. It mainly helps the project management team to quantify and categories the defects/issues according to sources (e.g. engineering defects, acoustic defects, setup problems, etc)
10. B. "Inspection” is what the team is doing on individual drawings; however, the entire exercise of random selection and inspecting a work product is known as “Statistical Sampling”
11. A
12. D
13. D
14. D
15. B

For training and consulting go to --->    www.pmexpertinc.com

Project Scope Management


Assess your knowledge level  on Project Scope Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions

Click to Start  >>>Project Scope Management - Online Sample Test 


Process Names - Project scope management
  • Plan Scope Management
  • Collect Requirements 
  • Define Scope
  • Create Work Breakdown Structure
  • Control Scope
  • Validate Scope







Monday, May 16, 2011

Project Integration Management

Assess your knowledge level  on Project Integration  Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions


Click to Start  >>>Project Integration Management - Online Sample Test


Process Names - Project scope management

  • Develop Project Charter
  • Develop Project Management Plan
  • Direct and Manage Project Work
  • Manage Project Knowledge
  • Monitor and Control Project Work
  • Perform Integrated Change Control
  • Close Project or Phase






PMI ACP Open Assessment - 100 Questions

PMI - ACP Practice tests  - Based on Latest Exam pattern Two Practice test $15.00 USD Three Practice test $20.00 USD Five ...