Project Schedule Management

PMP Portal <

Assess your knowledge level  on Project Schedule Management by attempting the following online test  from PM Expert -20 Randomly Selected Questions

Click to Start  >>>Project Schedule Management - Online Sample Test


Process Names - Project schedule  management



  • Plan Schedule Management
  • Define Activities
  • Sequence Activities
  • Estimate Activity Duration
  • Develop Schedule
  • Control Schedule



Following are Additional questions for Practice 

1. An activity has a duration estimate that is best case = 30 day, most likely =44 days, and worst case =62 days. What is the three point estimate for this activity
A. 44.67 days
B. 34.67 days
C. 5.33 days
D. 59.33 days

2. Which Develop Schedule tool inserts non-working buffer time between schedule activities?
A. Critical chain method
B. Critical path method
C. Resource leveling
D. Schedule modeling

3. The amount of time that an activity may be delayed without extending the critical path is
A. Lag
B. Grace Period
C. Free Factor
D. Slack

4. Activity Definition is typically performed by which of the following:
A. Project Manager who created the WBS
B. Project Team Members responsible for the work package
C. Project Officer
D. Project Stakeholder

5. Which of the following is not an activity attribute:
A. Person responsible for the activity
B. Location where to perform the activity
C. Time when to perform the activity
D. Leads and Lags

6. Which of the following does NOT generate changes to the Project documents:
A. Define Activities
B. Sequence Activities
C. Estimate Activity Resources
D. Estimate Activity Durations


7. Which of the following may generate a milestone list:
A. Define Activities
B. Sequence Activities
C. Estimate Activity Resources
D. Estimate Activity Durations

8. In PDM, which of the following relationships is rarely used:
A. Finish-to-Start
B. Start-to-Finish
C. Start-to-Start
D. Finish-to-Finish

9. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
A. Finish-to-Start
B. Start-to-Finish
C. Start-to-Start
D. Finish-to-Finish

10. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
A. ADM
B. PDM
C. A dependency with lag
D. A dependency with lead

11. The following BEST describes a subnetwork:
A. Precedence Diagramming Method [PDM]
B. Arrow Diagramming Method [ADM]
C. Fragment Network
D. Activity-On-Node [AON]

12. What-if scenario analysis is done as a part of which process:
A. Sequence Activities
B. Define Activities
C. Develop Schedule
D. Control Schedule

13. AON refers to:
A. Precedence Diagramming Method [PDM]
B. Arrow Diagramming Method [ADM]
C. Fragment Network
D. Mandatory Dependencies

14. AOA refers to:
A. Precedence Diagramming Method [PDM]
B. Arrow Diagramming Method [ADM]
C. Fragment Network
D. Mandatory Dependencies

15. Activity Resource Requirements is an input to which of the following processes:
A. Estimate Activity Durations
B. Control Schedule
C. Estimate Activity Resources
D. Sequence Activities

16 Based on the diagram below answer the following questions

A)     ABC
B)      DBC
C)      DEF
D)     All of the above

17.  Based on the Diagram below answer the following question

All the relationships in the diagram are Finish –to – Start except for B and E which is Finish- to – Finish with E finishing 3 days later. There is a lag of 3 days between E and F. Based on this the duration of the project is

A)     12 days
B)      14 days
C)      16 days
D)     18 days

18. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6 days. What is the minimum total duration between the Milestones A and B? 


    1. 36 days  
    2. 37 days  
    3. 39 days
    4. 42 days

19. In which of the following resource optimization technique the critical path doesn't change and hence completion date is not changed

A)     Resource Levelling
B)      Resource Smoothing
C)      Resource Shifting
D)     Critical Chain

20. You’re managing a software project. You’ve created the schedule, and you need to figure out which activities absolutely cannot slip. You’ve done critical path analysis, identifying the critical path and calculating the early start and early finish for each activity. Which activities cannot slip without making the project late 


A) The ones with the biggest difference between ES and LS
b.)The activities with ES-LS =0
c.)The activity with the most lag
D.) The last activity in the project, because it has no float

21, Answer the question based on the sub net shown below.



A) 3,3
B) 2,3
C) 1,3
D) 6, 8



Answers

1. Answer A
2. Answer A
3. Answer D
4. Answer: B
5. Answer: C Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
6. Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
7. Answer: A
8. Answer: B
9. Answer: A
10. Answer: D Note that this dependency can be represented by both ADM and PDM techniques.
11. Answer: C
12. Answer: C
13. Answer: A
14. Answer: B
15. Answer: A One of the outputs of Estimate activity resources is Activity Resource Requirements. Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the sequence.
16. Answer:  A ABC and the length is 18 days
17. Answer : D
18 Answer: B
19 Answer :B
20.Answer B
21 Answer D

For training and consulting go to --->    www.pmexpertinc.com

1 comment:

  1. Visit www.pmexpertinc.com for courses on Project Management
    PMP, PRINCE2,PMI-ACP

    ReplyDelete