PMP Formula Key and PMP Concepts
Earn Value
Formulas
|
PV (Planned Value) = BCWS (Budgeted Cost of Work
Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work
Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work
Performed)
SV = EV – PV (A negative value indicates that project is behind schedule)
CV = EV – AC (A negative value indicates that project is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV) Use when
variances are atypical
EAC = AC + [(BAC-EV)/CPI] Use when
variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BAC – EAC
ETC = BAC – EV Use when variances are
atypical
ETC = (BAC – EV)/CPI Use when
variances are typical
ETC = EAC – AC Use when
original estimates were flawed
TCPI - To complete performance Index
TCPI = BAC-EV/BAC-AC
TCP (EAC Based) = BAC-EV/EAC-AC
|
Calculating Slack or Floa t
What is Free Float?
|
Critical path is the longest path in the project network diagram and it determines the planned duration. A project can have more than one critical path. Critical path may change during the project life cycle.
Total Float (also called Slack, Float, or Project
Float) is the total amount of time an activity can be delayed without
delaying the project finish date.
Free Float/Slack is the amount of time an
activity can be delayed without delaying its successor (following activity).
Ø LS – ES: Calculates slack with forward pass
Ø LF – EF: Calculates slack with backwards pass
Lag Time: Inserted wait time between
activities
Lead Time: Overlapping activities, also called paralleling or fast tracking. “Lead In; Lag Out”
For the activities on the critical path float is zero.
Free Float – Amount of delay we can afford in a predecessor
without delaying the early start of successor.
|
Three Point Estimates, or PERT
|
PERT =
PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic,
Pessimistic, and Most Likely
For Beta
or Normal Distribution
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (s) = (P – O)/6
For Triangular Distribution
Mean Estimates = 0+M+P/3
|
Accuracy of Estimates
|
Order of Magnitude:-25% to +75%
Budget Estimate:-10% to +25%
Definitive Estimate:-5% to +10%
|
Channels of Communication
|
Between Team Members = N(N-1)/2 where N is the no
of team members
|
Project Selection Financials or project Appraisal
|
NPV (Net
Present Value) = FV/(1+r)n
FV= Future Value, r= interest rate, n= no. of
time periods
Higher NPV is better
IRR
(Internal Rate of Return) = Solve the NPV equation for “r”
Also called Hurdle Rate
Higher IRR percentage is better
BCR
(Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is
better
ROI
(Return on Investment) = Earnings/Investment
Higher ROI is better
Payback Period = Time to recover cost of the
project
Lower payback period is better
All the Appraisal techniques mentioned above help in assessing the business justification of the project.
|
Thursday, January 1, 2015
PMP ITTOs- Input, Tools & Techniques and Outputs
Click the link below to download the chart on - Input, Tools & Techniques and Outputs for all the 49 processes based on PMBOK Sixth Edition.
Download Process Chart
Download Process Chart
Sunday, December 7, 2014
PMP VS PRINCE2
The PMBOK Guide is
knowledge or a collection of recommendations and best practices, while PRINCE2 is a methodology.
Following table highlights some of the key differences.
PMBOK Guide
|
PRINCE2
|
Knowledge or a collection of recommendations and
best practices (Explains what you should know)
|
Methodology (explains what you should do)
|
Descriptive (explains the good practices)
|
Prescriptive (tells you what to do)
|
PMBOK consists of the tools and techniques of
project management and is a guide telling how things could be done whereas
PRINCE2 is a methodology, with a clear process, steps and templates.
|
Answers WHAT, WHEN, and WHOM questions. PRINCE2
explains exact set of processes or steps to be followed and templates.
A project manager following PRINCE2 is very clear about steps to be followed
|
PMP is centred around the project manager and emphasises on
what a project manager should and his roles and responsibilities
|
In PRINCE2 the focus is on three levels of management,
Directing (Project Board), Managing (Project Manager) and Delivering (Team
Manager). The roles and responsibilities corresponding to each role in all
the three levels is defined very clearly
|
PRINCE2 is popular in countries such as UK, Australia and certain European countries such as Netherlands, Denmark and Germany. PMP is more popular in North America. A good project manager should have both the PRINCE2 and PMP certifications. Even if one doesn’t have both the certifications still at least one should be familiar with both. It is a popular scenario in UK after receiving the PRINCE2 certification, the project manager will supplement with PMP training while in North America, PMP members wants to take the PRINCE2 in order to get more on the Project Control and with an additional globally recognized certification.
Subscribe to:
Posts (Atom)
PMI ACP Open Assessment - 100 Questions
PMI - ACP Practice tests - Based on Latest Exam pattern Two Practice test $15.00 USD Three Practice test $20.00 USD Five ...
-
1. Scenario: Your project's cost baseline is $500,000. Midway through the project, you've spent $300,000, and the Earned V...
-
PMP Portal < 1. Scenario: You’re managing a software development project. A stakeholder requests a new feature that...
-